Five Applications have been received in Round 1 of the MD PSC Energy Storage Request for Applications Solicitation (pursuant to NGEA). Round 1 will seek to select 800 MWs of at least 4-hour, front-of-the-meter transmission connected energy storage. The PSC will issue a decision whether to approve one or more Applications by October 1, 2026.

Project NameOystercatcher Energy Storage
ApplicantCardinal Energy Storage East, LLC
Project Location (County)NW corner of Harford County, adjacent to the BGE Conastone Substation
Energy Storage TechnologyLithium Ion
Nameplate Capacity (MW)500
Storage Duration (Hours)6
Interconnecting UtilityBaltimore Gas & Electric
Project NameFourth Quarter BESS
ApplicantRWE Supply & Trading Americas, LLC
Project Location (County)21200 Martinsburg Rd, Dickerson, MD 20842 (Montgomery)
Energy Storage TechnologyLithium Iron Phosphate
Nameplate Capacity (MW)300
Storage Duration (Hours)4
Interconnecting UtilityPotomac Electric Power Company
Project NamePulaski Energy Storage
ApplicantPulaski Energy Storage LLC
Project Location (County)8337 Pulaski Highway Baltimore, Maryland 21237 (Baltimore)
Energy Storage TechnologyLithium Iron Phosphate
Nameplate Capacity (MW)135
Storage Duration (Hours)4
Interconnecting UtilityBaltimore Gas & Electric
Project NameChalk Point Storage
ApplicantChalk Point Reliability Storage LLC
Project Location (County)25100 Chalk Point Rd, Aquasco MD 20608 (Prince George’s)
Energy Storage TechnologyLithium Iron Phosphate
Nameplate Capacity (MW)400
Storage Duration (Hours)4
Interconnecting UtilityPotomac Electric Power Company
Project NameJade Meadow III Battery Storage
ApplicantJade Meadow III LLC
Project Location (County)1700 Russell Road, Barton, MD, 21521 (Garrett)
Energy Storage TechnologyLithium Ion
Nameplate Capacity (MW)40
Storage Duration (Hours)4
Interconnecting UtilityFirst Energy/Potomac Edison