The table below provides the expected timeline of the Maryland Public Service Commission Round 1 Energy Storage Capacity Credit Application Period. The Maryland Public Service Commission and Power Advisory reserve the right to adjust the schedule as needed.
| Request for Information (RFI) Issued | October 14, 2025 |
| RFI Responses Due | October 28, 2025 at 5pm ET |
| Solicitation Window Opens | December 24, 2025 |
| Applicant Webinar | January 8, 2026 |
| Application Submission Due Date | March 2, 2026 at 4 pm ET |
| Maryland Public Service Commission Project Selection | October 1, 2026 |